Cisco ONS 15454 Installation and Operations Guide, R3.2
March 2002
Chapter 6 Circuits and Tunnels
Creating DCC Tunnels
Figure 6-16 Selecting DCC tunnel end points
Step 5
Click OK.
Step 6 Put the ports hosting the DCC tunnel in service:
a. Double-click the card hosting the DCC in the shelf graphic or right-click the card on the shelf
graphic and select Open.
b. Click the Provisioning > Line tabs.
c. Under Status, select In Service.
d. Click Apply.
DCC provisioning is now complete for one node. Repeat these steps for all slots/ports that are part of
the DCC tunnel, including any intermediate nodes that will pass traffic from third party equipment. The
procedure is confirmed when the third-party network elements successfully communicate over the
newly-established DCC tunnel.